Frequently Asked Questions

General

BLCP Power Limited is one of the private power producers under the Electricity Generating Authority of Thailand (EGAT) initiated Independent Power Producer (IPP) project and generates up to 2x700 megawatt of power using high quality bituminous coal as fuel. The power plant uses environmentally responsible technology, the impact of which on the environment is well controlled. The power plant will produce electricity in an environmentally responsible and safe manner using well-established technologies and tried and proven operating practices.

BLCP Power will begin to prepare the land for construction in July 2002 and construction of the power plant will begin in July 2003. Construction will take up to 42 months and the plant will begin supplying electricity to EGAT in October 2006 from the first unit and in February 2007 from the second unit.

The site is located in the Map Ta Phut Industrial Estate Phase 2 under the 30-year-long term lease contract signed by June 30, 2000 with the Industrial Estate Authority of Thailand (IEAT). In line with other heavy industrial plants in the nearby location, the plant is also required to comply with all terms and conditions as stipulated by the lease contract, and to meet all environmental compliance as stipulated in various permits or licenses, granted by the authority. 

BLCP Power Limited is a joint-venture between an affiliated company of Banpu Public Company Limited and the Electricity Generating Public Company Limited or EGCO Group, who both currently hold a 50 per cent shareholding in BLCP


EGAT issued an invitation for private companies to bid on the Independent Power Producer (IPP) power purchase project on December 15, 2537.

EGAT announced the winners of the IPP Phase 2 project bid on December 20, 2539, with BLCP Power Company being one of the successful bidders at that time. After December 20, 2539, EGAT and BLCP negotiated the Power Purchase Agreement (PPA) and signed it on November 19, 2540. Under the agreement, the Company was scheduled to supply electricity to EGAT's system on October 1, 2545, for Unit 1, and February 1, 2546, for Unit 2. Subsequently, an economic crisis occurred in Thailand, significantly reducing domestic electricity consumption. EGAT therefore issued a letter dated December 25, 2541, requesting a four-year postponement of BLCP's scheduled electricity supply to EGAT's system, asking the Company to supply electricity to EGAT's system on October 1, 2549, for Unit 1, and February 1, 2550, for Unit 2.

The Company accepted EGAT's request and fully cooperated in negotiating the Power Purchase Agreement Amendment (PPA Amendment) due to significant changes in the original agreement, signing the PPA Amendment on December 30, 2542. The Company negotiated to lease land for the construction of the power plant in the Map Ta Phut Industrial Port Phase 2 area with the Industrial Estate Authority of Thailand (IEAT) and signed the land lease agreement on June 30, 2543, to comply with the obligations of the amended PPA. After signing the initial Power Purchase Agreement (PPA), the Company conducted environmental impact assessment studies for the power plant and the coal handling port to comply with the PPA, commencing studies in 2539. The environmental impact assessment reports for the power plant and the coal handling port were approved by the Office of Environmental Policy and Planning on January 11, 2544, and February 25, 2545, respectively.

About BLCP Power Plant

The total area will cover 602 rais. The plant's maximum power generating capacity is approximately 1,434 megawatts.

The power plant is comprised of 3 main parts: the power plant, coal unloading facilities and coal stock yards.

No. The BLCP power plant project was originally proposed to be located in Rayong Province in 1996 and has not been moved from another province.

BLCP is an electricity-generating power company that has been accepted worldwide for using technology proven to reduce the impact on our environment. The company manages the system as efficiently as possible with the aim of achieving its business vision of “becoming a role model for coal-fired power plants in Thailand”.

In terms of quality, bituminous coal is better than lignite coal due to its high heating value, which is almost double that of lignite. Additionally, bituminous coal has a lower sulfur content with BLCP agreeing to not use coal with a sulfur content in excess of 0.7%. An average sulfer content throughout the year should not be exceeding 0.45%. Lignite coal has a sulfur content of approximately 3-5%.

It is imported from Australia and Indonesia.

No, the plant is designed to use only bituminous coal. Lignite coal cannot be used as a substitute.

The coal is transported by ship directly to the power plant. A semi-closed and closed conveyor belt system is used to convey coal from the Coal Unloading Facilities to the power plant itself. Water will be sprayed to prevent coal dust from spreading to the water or surrounding air at unloading hoppers. The water used in this process will be collected and treated for reuse. 

The power is necessary to facilitate continued economic growth and prosperity as outlined in the Kingdom of Thailand’s development plans.

The use of private international companies to build, own and operate the power plant allows EGAT to reduce its investment requirements and allows the Thai electricity system to become more efficient as international companies bring different perspectives and skills which can add value to the operations of the Thai electricity network.

Benefit to the country
BLCP can reduce the government’s burden in large project investment to maintain the country’s power reserve.

Benefit to the community
BLCP provides job opportunities for up to 1,400 people during the peak period of construction and 280 employees will be hired during operation. This does not include benefits that local people within the area will have when the power plant starts operation and benefits for  the associated businesses, which are necessary to support the power plant’s operations such as the food industry and other industries.
BLCP generates income for the community in terms of taxes, especially household, land and business taxes totaling around 20 million baht annually. This figure does not include value-added tax, income and commercial taxes.
The company has a policy to contribute to a better quality of living for the local people in many ways including;
Promotion of occupational and income earning development
Educational and skill development for children/young people
Environmental development and health improvement of people in the community 
The company will consider activities that respond to the needs of, and are appropriate for, each community.

BLCP was selected because of its low price of electricity, which is among the world’s lowest cost of electricity, and below EGAT’s costs to produce electricity.  The cost per unit of electricity generated from a natural gas-fueled power plant is higher than when coal is used as fuel. This is due to the price of natural gas, which is affected by the movement of oil prices in the global market. At present, Thailand uses natural gas for up to 70% of its existing power production while coal used as fuel for only 19% of power production. The cost of fuel affects the price of electricity due to the price fluctuation value (Fuel Tariff, FT) which is calculated based on the average fuel price. Therefore, with higher use of low-cost fuel, power can be produced with a lower FT value so bringing down the price of electricity.   

Why a Coal-Fired Power Plant

For the U.S. and Europe, coal has been widely used for electricity generating. To balance their fuel usage not to be depending too much on one fuel which will result in a severe problem to the country in case of a shortage of the particular fuel, these countries have diversified to other alternative fuel, i.e. gas, nuclear and biomass.

For Asian region, new coal-fired power plants are being constructed in many countries, inclusive of Japan, Indonesia, China and Malaysia, the country with 10 times more reserve of gas than Thailand, due to the same reason. 


Thailand currently uses gas for its 70% of electricity generating. This ratio is too risky for the country. In the light of the gas shortage or an increase of oil price, there will be a severe damage to the country and the power price will be increased accordingly.


No, Banpu will not supply coal to BLCP as it does not have enough coal with the required consistently high quality.

ภาวะโลกร้อนเกิดจากการใช้พลังงานในชีวิตประจำวันของทุกๆ คน ซึ่งพลังงานส่วนใหญ่จะถูกใช้ในการผลิตสินค้าและการขนส่ง การผลิตพลังงานไฟฟ้าทั้งที่ใช้เชื้อเพลิงจากถ่านหิน น้ำมัน ก๊าซธรรมชาติ หรือแม้แต่การผลิตพลังงานไฟฟ้าจากเขื่อนพลังน้ำ ก็ล้วนแต่เป็นส่วนหนึ่ง ที่ก่อให้เกิดภาวะโลกร้อน เนื่องจากการสร้างเขื่อนจะต้องมีการตัดต้นไม้ ซึ่งจะทำให้ความสามารถในการดูดซับก๊าซคาร์บอนไดออกไซด์ของโลกเราลดลงอย่างไรก็ตาม เมื่อพิจารณาถึงก๊าซต่าง ๆ ที่มีส่วนทำให้เกิดภาวะโลกร้อน จะเห็นว่าการใช้เชื้อเพลิงถ่านหินในการผลิตกระแสไฟฟ้า จะทำให้เกิดก๊าซคาร์บอนไดออกไซด์ ซึ่งมีศักยภาพที่จะก่อให้เกิดภาวะเรือนกระจก (Global Warming Potential หรือ GWP) เพียงแค่ 1 เท่า เมื่อเทียบกับการผลิตไฟฟ้าโดยใช้ก๊าซธรรมชาติเป็นเชื้อเพลิง ซึ่งจะมีมีเทนเป็นองค์ประกอบหลัก เมื่อเกิดการรั่วไหลออกสู่สิ่งแวดล้อมจะมีศักยภาพที่จะก่อให้เกิดภาวะเรือนกระจกถึง 21 เท่า
หากจะเปรียบเทียบในระดับประเทศต่างๆทั่วโลก ผลกระทบที่จะก่อให้เกิดปรากฎการณ์เรือนกระจกที่เกิดจากอุตสาหกรรมต่างๆในประเทศไทยนับว่ามีน้อยเมื่อเทียบกับประเทศที่พัฒนาทางอุตสาหกรรม อาทิ สหรัฐอเมริกา ซึ่งน่าจะจับตามองเป็นอย่างมากในเรื่องของการให้ความร่วมมือเพื่อการแก้ไขอย่างรีบด่วน

บริษัทฯ ให้ความสำคัญกับเรื่องสิ่งแวดล้อมตั้งแต่การเลือกใช้เทคโนโลยีถ่านหินสะอาด ไปจนถึงการมีมาตรการในการป้องกันผลกระทบสิ่งแวดล้อม โดยการเลือกใช้เชื้อเพลิง คือ ถ่านหินบิทูมินัส ซึ่งเป็นถ่านหินคุณภาพดี มีปริมาณซัลเฟอร์ในถ่านหินต่ำ คือ มีปริมาณสูงสุดไม่เกินร้อยละ 0.70 และปริมาณเฉลี่ยต่อปีไม่เกินร้อยละ 0.45
หากจะเปรียบเทียบในระดับประเทศต่างๆทั่วโลก ผลกระทบที่จะก่อให้เกิดปรากฎการณ์เรือนกระจกที่เกิดจากอุตสาหกรรมต่างๆในประเทศไทยนับว่ามีน้อยเมื่อเทียบกับประเทศที่พัฒนาทางอุตสาหกรรม อาทิ สหรัฐอเมริกา ซึ่งน่าจะจับตามองเป็นอย่างมากในเรื่องของการให้ความร่วมมือเพื่อการแก้ไขอย่างรีบด่วน
การเลือกใช้เครื่องจักรในการผลิตกระแสไฟฟ้า ซึ่งเป็นเครื่องจักรที่มีเทคโนโลยีที่ทันสมัย พร้อมอุปกรณ์การดูแลสิ่งแวดล้อมที่มีประสิทธิภาพ โดยติดตั้งเครื่องกำจัดก๊าซซัลเฟอร์ไดออกไซด์ เลือกใช้เตาเผาที่มีการควบคุมการเกิดก๊าซออกไซด์ของไนโตรเจนให้มีปริมาณน้อย ติดตั้งเครื่อง ดักฝุ่นระบบไฟฟ้าสถิตย์ อากาศที่บำบัดแล้วจะถูกปล่อยออกทางปล่องซึ่งมีความสูงถึง 200 เมตร เพื่อลดปัญหาเรื่องมลภาวะทางอากาศ นอกจากนี้ ยังมีโรงบำบัดน้ำเสีย มีบ่อปรับค่าอุณหภูมิ และความเป็นกรด-ด่างของน้ำหล่อเย็นก่อนปล่อยลงสู่ทะเล เพื่อลดปัญหาเรื่องมลภาวะทางน้ำ
จัดระบบการติดตามตรวจสอบคุณภาพสิ่งแวดล้อม ทั้งทางน้ำและทางอากาศอย่างสม่ำเสมอ ด้วยเครื่องมืออัตโนมัติและตรวจสอบซ้ำโดยที่ปรึกษาด้านสิ่งแวดล้อม รวมทั้งให้ความร่วมมือ กับหน่วยงานด้านสิ่งแวดล้อมให้เข้ามาตรวจสอบได้
บริษัทฯยังได้ทำการพัฒนาป่าชายเลนร่วมกับเทศบาลนครระยองและประชาชนในพื้นที่รอบป่าชายเลนในพื้นที่ประมาณ 200 ไร่ ซึ่งสามารถปลูกป่าไดประมาณ 100,000 ต้น หรือสามารถลดการปล่อยก๊าซคาร์บอนไดออกไซด์ได้ประมาณ 25,000 ต่อปีถึงแม้ว่าจะไม่สามารถลดการระบายก๊าซดังกล่าวได้ไม่ทั้งหมดแต่ก็เป็นการแสดงเจตนารมณ์อย่างแน่วแน่ของบริษัทฯที่ต้องการเป็นส่วนหนึ่งที่จะลดภาวะโลกร้อน

โรงไฟฟ้าบีแอลซีพียึดนโยบายไม่ต้องการให้เกิดการปะทะหรือเกิดความรุนแรงใดๆทั้งต่อชีวิตและทรัพย์สินของฝ่ายใดฝ่ายหนึ่ง
โรงไฟฟ้าบีแอลซีพีมีนโยบายที่ชัดเจนในเรื่องความโปร่งใสตรวจสอบได้ และพร้อมให้ชุมชน เข้ามามีส่วนร่วมตรวจสอบโรงไฟฟ้าบีแอลซีพีได้ทุกขั้นตอน
โรงไฟฟ้าบีแอลซีพียึดถือและปฏิบัติตามระเบียบข้อบังคับเกี่ยวกับมาตรฐานต่างๆ ตามที่ระบุไว้ ในรายงานการวิเคราะห์ผลกระทบสิ่งแวดล้อม (Environment Impact Assessment : EIA) และมาตรฐานการควบคุมผลกระทบต่อสิ่งแวดล้อมอย่างเคร่งครัด พร้อมทั้งมีการให้ความรู้ แก่ผู้ที่เกี่ยวข้องและเปิดเผยข้อมูลอย่างโปร่งใสและต่อเนื่องตลอดเวลา รวมถึงการเข้าไปอธิบาย และตอบคำถามให้แก่องค์กรเพื่อการพัฒนาต่างๆ ที่เป็นที่ยอมรับในสังคมไทย เช่น สภาทนายความ และองค์กรสิทธิมนุษยชนแห่งประเทศไทย เป็นต้น
บริษัทฯ พร้อมที่จะรับฟังความคิดเห็นของผู้ที่มีส่วนเกี่ยวข้อง และเผยแพร่เอกสารต่างๆ ที่เกี่ยวข้องกับโครงการฯ ทั้งข้อมูลด้านเทคนิค ข้อมูลในการตรวจวัดคุณภาพสิ่งแวดล้อม และข้อมูลเกี่ยวกับกิจกรรมในการมีส่วนสนับสนุนชุมชนที่อาศัยอยู่โดยรอบ

โรงไฟฟ้าบีแอลซีพีพยายามลดการปล่อยก๊าซคาร์บอนไดออกไซด์ให้น้อยที่สุด โดยใช้ถ่านหิน บิทูมินัสซึ่งเป็นเชื้อเพลิงที่มีคุณภาพสูง และการออกแบบเตาเผาที่ก่อให้เกิดการเผาไหม้ที่สมบูรณ์ ดังนั้น ก๊าซคาร์บอนไดออกไซด์ที่ปล่อยออกมาจึงมีปริมาณน้อยมาก และโรงไฟฟ้าบีแอลซีพี จะพยายามรักษาประสิทธิภาพนี้ไปตลอดช่วงอายุการใช้งานของโรงไฟฟ้า
โรงไฟฟ้าบีแอลซีพีได้จัดให้มีระบบการจัดการพลังงาน และจัดทำโครงการอนุรักษ์พลังงาน อย่างต่อเนื่องทุกปี เพื่อเพิ่มประสิทธิภาพการใช้พลังงานในการผลิตไฟฟ้า ซึ่งจะช่วยลดปริมาณ ก๊าซคาร์บอนไดออกไซด์

บริษัทฯ ใช้บิทูมินัสแน่นอน บริษัทฯ มีสัญญาซื้อขายถ่านหินตลอดอายุโครงการ 25 ปี และมีการนำถ่านหินเข้ามาจากต่างประเทศโดยเรือ เที่ยวละประมาณ 1.5 แสนตัน นำเข้าปีละ 24 – 29 เที่ยวเรือ เฉลี่ย 2 ครั้ง/เดือน ทุกเที่ยวเรือจะมีการตรวจสอบโดยหน่วยงานกลาง และผลการตรวจวัดปริมาณซัลเฟอร์ในถ่านที่ส่งมาจะจัดส่งให้หน่วยงานที่รับผิดชอบคือ สผ. ทุกเที่ยวเรือ สำหรับความเป็นไปได้ที่จะนำถ่านหินประเภทลิกไนต์เข้ามาผสมด้วยได้หรือไม่นั้น เนื่องจากเครื่องจักรที่ออกแบบมาเพื่อใช้ถ่านหินที่มีค่าความร้อนสูงมากขนาดนี้จึงจะใช้งานได้ เนื่องจากถ่านหินประเภทบิทูมินัส 1 กก. ให้ความร้อนเท่ากับลิกไนต์ประมาณ 2 กก. ตามหลักการนี้แม้แต่เรื่องต้นทุนก็รับไม่ได้แล้ว และ บริษัทฯ ได้มีมาตรการลดผลกระทบสิ่งแวดล้อม โดยการติดตั้งอุปกรณ์ติดตั้งติดตามตรวจสอบ บริเวณปล่องระบายอากาศ ซึ่งเป็นการตรวจสอบตลอด 24 ชั่วโมง และจะออนไลน์ไปที่ กนอ. และกรมควบคุมมลพิษ เพื่อยืนยันว่าบริษัทฯ ดำเนินการผลิตเหมือนกันตลอดเวลา และเนื่องจากลิกไนต์ในปัจจุบันพบที่จังหวัดลำปางอยู่ภาคเหนือ ในขณะที่โรงไฟฟ้าตั้งอยู่ที่ จ.ระยอง หากต้องขนส่งถ่านหินลงมาเป็นไปได้ 2 ทาง คือทางรถยนต์ กับทางรถไฟ ซึ่งค่าขนส่งเฉลี่ยประมาณ 2 บาท/กม./ตัน ฉะนั้นค่าขนส่งจากจังหวัดลำปางมาที่มาบตาพุดสูงกว่าเชื้อเพลิงที่นำเข้าโดยเรือ จึงเป็นไปไม่ได้ที่บริษัทฯ จะขนส่งลิกไนต์จากแม่เมาะมาใช้ที่โรงไฟฟ้า จ. ระยอง

โรงไฟฟ้าบีแอลซีพีดำเนินนโยบายโดยยึดหลักบรรษัทภิบาล (Corporate Governance) กล่าวคือ ใช้หลักคุณธรรม นิติธรรม ความคุ้มค่า ความโปร่งใส สามารถตรวจสอบได้ ความรับผิดชอบต่อสังคม การมีส่วนร่วมกับชุมชน และการดูแลรักษาสิ่งแวดล้อม ทั้งนี้เพื่อสร้างความไว้วางใจ สร้างความรู้และความเข้าใจที่ถูกต้องให้แก่ชุมชนหรือผู้ที่เกี่ยวข้องอย่างไม่ย่อท้อ
นอกจากนี้บริษัทฯ ยังได้เข้าไปมีส่วนร่วมในกิจกรรมชุมชนสัมพันธ์ต่างๆ อย่างต่อเนื่องและสม่ำเสมอ เพื่อบริษัทฯ จะได้มีความรู้และเข้าใจความต้องการของชุมชนอย่างถูกต้องทันต่อสถานการณ์ที่เปลี่ยนแปลงไปตลอดเวลา ทั้งยังช่วยทำให้บริษัทฯ สามารถประมวลผล ปรับปรุงการดำเนินงานด้านประชาสัมพันธ์ การติดต่อสื่อสารและงานชุมชนสัมพันธ์ เพื่อตอบสนองความต้องการของชาวชุมชนได้อย่างทันท่วงที มีประสิทธิภาพและประสิทธิผล อีกทั้งบริษัทฯ เชื่อมั่นว่าการออกไปพบปะพูดคุยและการอธิบายข้อคับข้องใจต่างๆ ของชุมชน น่าจะช่วยคลายข้อกังวลใจหรือช่วยแก้ไขปัญหาของชุมชนได้อย่างถูกต้องทั้งในปัจจุบันและในอนาคต

โรงไฟฟ้าบีแอลซีพีตระหนักถึงความสำคัญของชุมชนโดยรอบโรงไฟฟ้า จึงมีนโยบายพัฒนาชุมชนต่างๆในเขตมาบตาพุดผ่านโครงการต่างๆที่ได้รับความสนใจและการร่วมมือจากชุมชนต่างๆ อาทิ
การประชุมคณะกรรมการไตรภาคี (Tripartite Committee Meeting) จัดขึ้นเพื่อสร้างความรู้ ความเข้าใจที่ถูกต้องในเรื่องโรงไฟฟ้าถ่านหิน สร้างการมีส่วนร่วม และเพื่อแจ้งผลการดำเนินงาน กิจกรรม ข้อมูลข่าวสารของโรงไฟฟ้าฯ ให้คณะกรรมการฯ และผู้เข้าร่วมประชุมทราบอย่างต่อเนื่องและสม่ำเสมอ รวมทั้งรับฟังข้อคิดเห็น ข้อเสนอแนะ ปัญหา หรือผลกระทบต่างๆ ที่อาจจะเกิดจากกิจกรรมของโรงไฟฟ้าฯ เพื่อนำมาปรับปรุงแก้ไข และหาทางป้องกันร่วมกัน
โครงการทุนการศึกษา “น้อง ๆ เรียนดีกับบีแอลซีพี” (BLCP Scholarship) โครงการนี้จัดขึ้นเพื่อส่งเสริมให้เยาวชนในพื้นที่ได้มีโอกาสพัฒนาศักยภาพของตนเอง ช่วยแบ่งเบาภาระค่าใช้จ่ายภายในครอบครัวช่วงที่เปิดเทอมและมีส่วนร่วมในการพัฒนาคุณภาพชีวิตชุมชน ด้านการศึกษา
โครงการรักษ์ป่าชายเลนกับ บีแอลซีพี (BLCP Mangrove Forest Planting) เป็นโครงการระยะยาว 5 ปี (2551 – 2555) ณ สมุทรเจดีย์กลางน้ำ จ. ระยอง จัดขึ้นเพื่อพัฒนาผืนป่าชายเลนผืนสุดท้ายของชาวระยอง ซึ่งมีจำนวนประมาณ 200 ไร่ และเพื่อเป็นแหล่งธรรมชาติศึกษาแก่อนุชนรุ่นหลังและผู้ที่สนใจทั่วไป รวมทั้งเป็นการปลูกฝังจิตสำนึกในการรับผิดชอบต่อสังคมและสิ่งแวดล้อมให้กับพนักงาน และชาวระยอง ด้วยการสรรสร้างโลกสวยด้วยมือเรา
โครงการนำร่องการจัดการน้ำเสียระดับครัวเรือน (Grey Water Pilot Project) เพื่อศึกษาและพัฒนารูปแบบระบบการจัดการและเทคโนโลยีการจัดการน้ำเสียระดับครัวเรือน เป็นการส่งเสริมการมีส่วนร่วมและพัฒนาศักยภาพขององค์กรภาคประชาชนในการจัดการน้ำเสียของชุมชน
โครงการอิฐบล็อกผสมเถ้าถ่านหิน (Fly Ash Cement Blocks) เป็นโครงการที่แสดงให้เห็นถึงประโยชน์ของเถ้าถ่านหิน(เถ้าลอย) ด้วยการสร้างมูลค่าเพิ่ม โดยการนำไปใช้เป็นส่วนผสมในการทำอิฐบล๊อก (บล๊อกปูพื้นถนน) และยังเป็นการสร้างงาน สร้างอาชีพ และรายได้ให้กับชุมชนอย่างต่อเนื่องและสม่ำเสมอ
ผักปลอดสารพิษ เพื่อเศรษฐกิจพอเพียง (Hydroponics Vegetables Farm Project) เป็นโครงการที่ ส่งเสริมให้ผู้บริโภคผักมีสุขภาพแข็งแรง รวมทั้งสร้างเสริมอาชีพและรายได้ให้แก่ผู้ขอรับโครงการ เช่นนายทหารชั้นผู้น้อย และเป็นอาหารกลางวันสำหรับเด็กในโรงเรียน
โครงการมัคคุเทศน์น้อยบีแอลซีพี (BLCP Junior Guide) บริษัทฯ ได้ริเริ่มโครงการนี้มาตั้งแต่ปี พ.ศ. 2550 และจัดอย่างต่อเนื่องในทุกๆ ปี เพื่อส่งเสริม พัฒนาความรู้ ความสามารถ และฝึกฝนให้เยาวชนมีทักษะการสื่อสารที่ดี มีความเชื่อมั่นในตนเอง กล้าคิด กล้าทำ กล้าแสดงออกในทางที่ถูกที่ควร สามารถแก้ปัญหาเฉพาะหน้าได้ รวมถึงช่วยพัฒนาให้เยาวชนที่เข้าร่วมโครงการสามารถเป็นผู้นำที่ดีได้ในอนาคต
นอกจากนี้บริษัทฯ ได้จัดตั้ง “อาคารพลังงานเคียงสะเก็ด” (Kiang Saket Energy Center; KSEC) เพื่อเป็นศูนย์กลางการเรียนรู้ด้านพลังงานแก่นักเรียน นิสิต นักศึกษา ชุมชน และบุคคลที่สนใจทั่วไป ภายในอาคารจัดให้มีห้องนิทรรศการต่างๆ ที่น่าสนใจเป็นอย่างยิ่ง โดยเน้นการสร้างเสริมความรู้ และความเข้าใจที่ถูกต้องเกี่ยวกับพลังงานประเภทต่างๆ

กลุ่มเพื่อนชุมชนกำเนิดขึ้นโดยกลุ่มผู้ประกอบการอุตสาหกรรมในมาบตาพุด จังหวัดระยอง ร่วมมือกันก่อตั้ง โดยมีวัตถุประสงค์พลิกวิกฤติมาบตาพุดให้เป็นโอกาสในการร่วมมือกันทำให้ดีกว่ากฏหมายกำหนด ยกระดับมาตรฐานโรงงานอุตสาหกรรมที่เป็นมิตรต่อสิ่งแวดล้อม ส่งเสริมคุณภาพชีวิตชุมชน เพื่ออุตสาหกรรมและชุมชนอยู่ร่วมกันอย่างยั่งยืน
สมาชิกในช่วงก่อตั้ง ประกอบไปด้วย บริษัท ปตท จำกัด (มหาชน) บริษัท เอสซีจี จำกัด (มหาชน) บริษัท บีแอลซีพี เพาเวอร์ จำกัด (มหาชน) กลุ่มบริษัทโกวล์ และบริษัทดาว เคมิคอล ประเทศไทย จำกัด

เป็นการทำงานร่วมกัน โดยการส่งผู้แทนมาร่วมในคณะทำงาน ซึ่งมี 3 คณะหลัก คือ
คณะทำงานปฏิบัติการโรงงานสีเขียว (Green Operation) มุ่งยกระดับมาตรฐานการจัดการสิ่งแวดล้อมของอุตสาหกรรมในมาบตาพุดให้ดีกว่า EIA หรือมาตรฐานกำหนด มีแผนงานเร่งด่วนในการลดสารอินทรีย์ระเหยง่าย (VOC) การควบคุมกลิ่น การควบคุมและลดการปล่อย Flare ให้ดีกว่าที่มาตรฐานกำหนด เพื่อพัฒนาอุตสาหกรรมสะอาดที่ยั่งยืน
คณะทำงานดูแลเอาใจใส่ชุมชนเพื่อคุณภาพชีวิตที่ดี (Beyond CSR) มุ่งพัฒนาสุขภาพและการศึกษาของคนในชุมชน โดยดูแลตรวจสุขภาพ และร่วมมือกับภาครัฐในการตรวจสุขภาพให้กับชุมชนเพื่อใช้เป็นฐานข้อมูลอย่างเป็นระบบ สนับสนุนบุคลากรด้านการพยาบาลโดยให้ทุนการศึกษาแก่นักศึกษาพยาบาล 200 ทุน รวมทั้ง เพิ่มศักยภาพและโอกาสให้กับเยาวชนในการศึกษาต่อในระดับอุดมศึกษา พัฒนาคุณภาพโรงเรียนให้ทัดเทียมกับโรงเรียนในระดับแนวหน้าของประเทศ และจัดทุนการศึกษาแบบต่อเนื่องจนถึงระดับอุดมศึกษา
คณะทำงานสื่อสารเสริมสร้างความเข้าใจ (Communication) มุ่งเผยแพร่ความรู้ความเข้าใจ และสร้างการมีส่วนร่วมกับชุมชนอย่างเปิดเผยและโปร่งใสเกี่ยวกับการดำเนินการด้านสิ่งแวดล้อมและความปลอดภัย โดยจะจัดตั้งศูนย์เพื่อนชุมชน เพื่อเป็นศูนย์รับข้อร้องเรียนให้เกิดการประสานงานและแก้ปัญหาอย่างรวดเร็ว ทั้งเป็นศูนย์ให้ความรู้แก่คนในชุมชน นอกจากนี้ ยังให้ความสำคัญกับการสื่อสารและซักซ้อมเหตุฉุกเฉินร่วมกับชุมชนให้ครบทุกชุมชน ตลอดจนการจัดเวทีชุมชนและรับฟังเสียงชุมชน

หลังจากเปิดศูนย์แล้ว จะมีการสื่อสารพ่วงไปกับกิจกรรม CSR ของกลุ่มเพื่อนชุมชน และแต่ละบริษัท นอกจากนี้ ยังมีเว็บไซต์ และสายด่วน 038 685 666 ที่จะเป็นอีกช่องทางในการเผยแพร่ข่าวสารต่างๆ ไปยังชุมชนด้วย
นอกจากนี้บริษัทฯ ได้จัดตั้ง “อาคารพลังงานเคียงสะเก็ด” (Kiang Saket Energy Center; KSEC) เพื่อเป็นศูนย์กลางการเรียนรู้ด้านพลังงานแก่นักเรียน นิสิต นักศึกษา ชุมชน และบุคคลที่สนใจทั่วไป ภายในอาคารจัดให้มีห้องนิทรรศการต่างๆ ที่น่าสนใจเป็นอย่างยิ่ง โดยเน้นการสร้างเสริมความรู้ และความเข้าใจที่ถูกต้องเกี่ยวกับพลังงานประเภทต่างๆ

After the center opens, communication will be integrated with the CSR activities of the Community Friends Group and each company. Additionally, a website and hotline 03 892 5100 will serve as other channels for disseminating information to the community.
Furthermore, the Company established the “Kiang Saket Energy Center” (KSEC) to serve as a learning hub for energy for students, university students, communities, and the general public. The building features various highly engaging exhibition rooms, focusing on enhancing knowledge and accurate understanding of different types of energy.

Environmental Impact Management and Monitoring

Measures on air ambient

The Station was designed by using the proven technology to reduce technical risks and to ensure environmental compliance.. Major equipments were installed as follows: 

  * Installation of burner for reducing oxide of nitrogen (Low NOx burner)  
 * Installation of Electrostatic Precipitator; ESP 
 * Installation of Flue Gas Desulphurization; FGD and
 * Construction of 200 meters high chimney

For air quality monitoring and checking, the Station has also installed an automatic air measuring instrument at the top of the chimney, and built four Air Quality Monitoring Stations (AQMS) within the specified vicinity of the power station.

Measures on water quality

Water supply in the Station can be categorized into 2 types as follows: 

Fresh water
It is designed for the usage of electricity generating process, the coal transportation at the coal unloading facilities, the maintenance activities at the coal stockyards, and general usage at offices for employees. The water is also needed at the waste water treatment plant including recycled again for the usage at the coal stockyard. 

Sea water 
The water will be pumped into the power plant at the cooling water intakes, and discharged back to the sea again at the outfalls after being properly treated of its chemical compositions, its temperature and its PH value for the purposes of environmental compliance.

 The Station also has equipments for protecting sea animals by installing 2-layer sieve in order to protect the sea animals from intruding into the cooling system.

In addition, the speed of sea water used in the cooling system is also controlled in order to enable the sea animals surviving in cooling water delivery canal. The system is checked and the annual maintenance of the equipment is executed, including the water quality and temperature around the power plant are regularly measured and checked. 

Ash 
Both fly and bottom ashes, arising from coal burning, can be commercially sold to the cement industry. At present, numerous studies showed that a variety of application can be made for additional value creation including ready-mix concrete, and simple reduction cost of this raw material. It is known that fly ash have been used for mixture with cement for construction of Khlong Tha Dan Dam in Nakhon Nayok Province.

Emission
The Station controls the percentage of sulfur content on per shipment basis within the range of 0.27-0.70%, and the average limit of 0.45% on per year basis. Based upon the plant design and the technical calculation, it is estimated that the Station can outperform all key parameters or limits as stipulated by the EIAs as follows. 
Dust at 43 mg/m3 against the regulatory limit of 120 mg/m3. Simply put, it is 64% better than the standard. 
Oxide of Sulfur (SO2) at 262 ppm. against the regulatory limit of 320 ppm. It is 18% better than the standard.  (However, the annual average is at 124 ppm., or  61% better than the standard).  
Oxide of Nitrogen (NOx) at 241 ppm against the regulatory limit of 350 ppm. It is 31% better than the standard.



Fuel:
⦁ Every shipment of coal will be analyzed by a third party to ensure that the coal meets specifications.

Air:
⦁ Dust density will be measured at 3 areas, north and south of the coal stock yards and at the Takuan community.
⦁ A Continuous Emission Monitoring System (CEMS) will be installed at the stack and manual monitoring will be carried out at the stack every 6 months.
⦁ 4 monitoring stations will be set up to automatically monitor air quality in the surrounding communities. Additional manual monitoring will be carried out around the plant every 6 months.

Water:
⦁ Water quality after treatment will be monitored every 6 months at the point of treatment and in the sea.
⦁ There are automatic sensors at the water release site to monitor temperature and acidity. The sensors are online to a control center and will sound an alarm should the water temperature or acidity exceed the set limits.
⦁ BLCP will monitor seawater temperatures at 13 locations 500 meters from the water release site every 3 months.

Air Quality Impact Monitoring

น้ำที่ใช้ในโรงไฟฟ้าฯ แบ่งออกเป็น 2 ประเภท ได้แก่
น้ำจืด (Fresh Water ) คือ น้ำที่โรงไฟฟ้าฯ นำไปใช้ในกระบวนการผลิต ท่าเรือ ลานกองถ่านหิน และภายในอาคารสำนักงาน โดยมีการจัดการน้ำเสีย ดังนี้ * จัดให้มีโรงบำบัดน้ำเสีย (Waste Water Treatment Plant) * น้ำฝนจากท่าเรือและลานกองถ่านหิน จะถูกบำบัดนำกลับมาใช้ใหม่ (Recycle)
น้ำทะเล (Sea Water) ถูกสูบเข้ามาเพื่อใช้หล่อเย็นและใช้ในระบบบำบัดก๊าซซัลเฟอร์ไดออกไซด์ โดยติดตั้งตะแกรง 2 ชั้น (Traveling Screen and Bar Screen) เพื่อป้องกันไม่ให้สิ่งมีชีวิต (สัตว์ทะเล) เล็ดลอดเข้ามาเข้ามาในระบบหล่อเย็น รวมทั้งได้มีการควบคุมความเร็วของน้ำทะเลที่สูบเข้ามาใช้ในการหล่อเย็น โดยตะแกรงดังกล่าวจะช่วยให้สิ่งมีชีวิตที่อาจเล็ดลอดเข้ามา สามารถหนีออกจากคลองส่งน้ำหล่อเย็น ได้โดยง่าย นอกจากนี้ บริเวณจุดปล่อยน้ำหล่อเย็นได้ดำเนินการติดตั้งบ่อเติมอากาศ เพื่อปรับค่าอุณหภูมิ และค่าความเป็นกรด-ด่างของน้ำ ก่อนที่จะระบายออกสู่ทะเล พร้อมทั้งได้มีการตรวจสอบระบบ และจัดทำแผนการบำรุงรักษาอุปกรณ์รายปี รวมถึงได้ดำเนินการติดตามตรวจสอบคุณภาพน้ำทะเล บริเวณโดยรอบโรงไฟฟ้าบีแอลซีพีอย่างต่อเนื่องและสม่ำเสมอ

เชื้อเพลิง
จะมีการตรวจสอบคุณภาพถ่านหินที่นำเข้าทุกเที่ยวเรือให้มีคุณภาพตามที่กำหนดจากหน่วยงานกลางที่เชื่อถือได้
อากาศ
จะมีการติดตามตรวจวัดปริมาณฝุ่นละออง 3 บริเวณ คือ ด้านเหนือ และด้านใต้ของลานกองถ่านหิน และที่ชุมชนตากวน
ติดตั้งอุปกรณ์ตรวจวัดคุณภาพอากาศแบบต่อเนื่อง (Continuous Emission Monitoring หรือ CEMs) ที่บริเวณกลางปล่อง และมีการตรวจวัดคุณภาพอากาศที่ระบายออกจากปล่อง โดยที่ปรึกษา ด้านสิ่งแวดล้อมทุก 6 เดือน
ติดตั้งสถานีตรวจสอบคุณภาพอากาศแบบต่อเนื่อง (Air Quality Monitoring Station หรือ AQMS) จำนวน 4 แห่ง รอบๆ โรงไฟฟ้าบีแอลซีพี และมีการตรวจวัดคุณภาพอากาศ ที่บริเวณสถานี AQMS โดยที่ปรึกษาด้านสิ่งแวดล้อมทุก 6 เดือน

ติดตามตรวจสอบคุณภาพน้ำที่ผ่านการบำบัดแล้ว โดยที่ปรึกษาด้านสิ่งแวดล้อมทุก 6 เดือน
ติดตั้งเครื่องมือติดตามตรวจสอบค่าอุณหภูมิ ค่าความเป็นกรด-ด่าง ค่าคลอรีนคงเหลือ และค่า CODแบบอัตโนมัติ ณ จุดปล่อยน้ำออกสู่ทะเล
ตรวจสอบการเปลี่ยนแปลงอุณหภูมิของน้ำทะเลในอ่าวมาบตาพุดจำนวน 13 จุด รอบๆ จุดปล่อยน้ำ โดยที่ปรึกษาด้านสิ่งแวดล้อมทุก 3 เดือน

Air:
⦁ A FGD (Flue Gas Desulfurization) system will treat oxide of sulfur. The power plant has been designed to reduce oxide of nitrogen to the extent possible.  

Water:
⦁ No water is released from the plant without prior treatment. A water treatment plant will be constructed to treat all water collected in the appropriate manner.  

Ash:
⦁ BLCP intends to sell ash on the open market. The cement industry is a potential consumer of such ash. 

⦁ The company is giving importance to environmental concerns by choosing environmentally responsible emissions control systems and implementing measures to reduce any environmental impact.
⦁ The company uses high quality bituminous coal as fuel, which has less than 0.70% sulfur and averages less than or equal to 0.45% per year (Sulfur in lignite coal used at the Mae Moh Lignite Power Plant is 3-5%)
⦁ The company selects the machines used in generating power and highly efficient equipment for environmental impact control, which are modern-technology devices equipped to eliminate emissions. The furnace is specifically designed to minimize emissions. A high efficiency electrostatic precipitator is utilized to minimize any particulate emissions, which are emitted through a 200-meter high stack. 
⦁ A continuous monitoring system will record seawater and air emissions conditions. The operational monitoring of the facility will be also supplemented by periodic manual tests by the appropriate government agencies. 

⦁ It is BLCP’s policy to be a responsible corporate citizen, which includes being fully compliant with all laws and regulations.  Additionally, BLCP has agreed to more stringent requirements than the Thai regulations require as a result of its environmental impact analysis.  If BLCP does not meet the Thai laws and regulations then it would fully expect to be subject to the penalties and damages stipulated by the Thai laws and regulations.

⦁ Seawater will be used as a scrubber agent. Oxide of sulfer will be transformed to bi-sulfer (HSO-4) which is normally available as a component of seawater. There will be no heavy metal from the FGD process.

Due to its EPC Turnkey Contract, the water treatment facility will be designed after the commencement of power plant’s construction.

⦁ The Industrial Estate Authority of Thailand (IEAT) is responsible for the   land reclamation program as part of its governmental mandate.  BLCP is a tenant of the Map Ta Phut Industrial Estate, and will carry out the reclamation necessary to construct the power plant in 2002 and 2003.  The reclamation process has been previously approved by the Thai government. 

A limited amount of dredging will be undertaken alongside the plant site in order to allow large coal vessels to unload coal.  The dredged material is approximately equal to the material necessary for the reclamation thus optimizing the efficiency of the dredging and reclamation works. 

The coal will be unloaded by large cranes onto a conveyor to be transported to the coal stockpiles to await use to generate electricity.  Water will be sprayed onto the coal at the various points in the process where coal dust could be produced.  The stockpiles will be compacted and either sprayed with water or protected by a cover to prevent dust from arising from the stockpiles.  It should be noted that the coal to be used by BLCP is actually a very hard substance, which is not conducive to producing a significant amount of dust.


The coal will be analyzed both on the loading of the ship and at the discharge at the power plant by a third party.

น้ำที่ปล่อยจากโรงไฟฟ้าลงสู่ทะเลนั้นเป็นน้ำทะเลที่ใช้ในการหล่อเย็นเครื่องจักร ไม่ใช่น้ำเสีย จึงไม่ส่งผลให้สัตว์น้ำตาย ทั้งนี้ ก่อนที่จะมีการปล่อยน้ำลงสู่ทะเล จะต้องมีการควบคุมคุณภาพน้ำ โดยการลดอุณหภูมิและปรับสภาพความเป็นกรด–ด่างก่อน นอกจากนี้ ทางบริษัทฯ ยังมีมาตรการติดตามตรวจสอบคุณภาพน้ำทะเลในรัศมี 500 เมตรรอบๆ จุดปล่อยอย่างต่อเนื่องและสม่ำเสมอ

น้ำหล่อเย็นใช้น้ำทะเลสูบเข้ามาในระบบเพื่อพาความร้อนของเครื่องจักรออกไปทำให้น้ำมีอุณหภูมิสูงขึ้น ได้รับการบำบัดโดยปล่อยออกไปที่บ่อพักและปั๊มอากาศเข้าไปเพื่อเพิ่มพื้นที่ผิวในการพาความร้อนออกไป หลังจากนั้นจะปล่อยออกสู่ท่อระบายน้ำยาว 500-600 ม. เพื่อปรับอุณหภูมิ จุดที่ปล่อยน้ำหล่อเย็นออกมาจะมีการตรวจวัดโดยระบบเครื่องมือโดยกรมโรงงานอุตสาหกรรมกำหนดว่าอุณหภูมิสูงสุดที่ปล่อยออกต้องไม่เกิน40°C อุณหภูมิรอบจุดปล่อยในรัศมี 500 ม. จะมีอุณหภูมิแตกต่างจากน้ำทะเลได้ไม่เกิน 3°C มีการตรวจวัดอุณหภูมิรอบๆ จุดปล่อยประมาณ 13 จุดรอบ โครงการตลอดอายุโครงการ 25 ปี

บริษัทฯ ได้ว่าจ้างบริษัทที่มีความชำนาญด้านการขุดลอกร่องน้ำจากประเทศเบลเยี่ยมโดยจะเริ่มขุดลอกร่องน้ำประมาณต้นปี 2546 การขุดลอกดังกล่าวจะใช้ เรือขุด Cutter Suction ด้วยหัวขุดทังสเตนคาร์ไบด์เจาะตะกุยตะกอนทราย ขณะเดียวกันก็สูบกลับขึ้นมา ซึ่งวิธีดังกล่าวมีประสิทธิภาพในการสูบตะกอนทราย ได้ถึง 90% ลำเลียงไปตามท่อ ลอยไปลงที่พื้นที่เช่าที่ต้องถมเพิ่ม นอกจากนี้ยังมีคณะกรรมการกำกับแผนปฏิบัติการป้องกันแก้ไขและติดตามตรวจสอบผลกระทบสิ่งแวดล้อมโครงการท่าเรือขนถ่ายถ่านหิน ซึ่งตั้งขึ้นตามเงื่อนไขที่ระบุใน EIA

ใช้น้ำทะเลวันละประมาณ 5.38 ล้านคิวบิกเมตรต่อวัน แพลงตอนที่สูบเข้าไปมีการพิสูจน์โดยนักชีววิทยาว่าตัวแพลงตอนเป็นประเภทใด และมีการพิสูจน์อีกเช่นเดียวกันว่าแพลงตอนส่วนนี้สามารถ Generate ได้ทุกวัน แต่อย่างไรก็ตามไม่ได้หมายความว่าบริษัทฯ มีสิทธิทำลายแพลงตอน แม้ทางบริษัทฯ ป้องกันไม่ได้แต่ส่ามารถสร้างทดแทนได้ บริษัทฯ ได้ปรึกษากับชุมชนโดยเฉพาะชุมชนประมง วิธีที่บริษัททำได้ก็คือไปสร้างใหม่ขึ้นมา เช่น การปล่อยปูในกระชังเพื่อให้เป็นระบบโซ่อาหารช่วงแรกของทะเลกลับไปสู่ทะเลรายละเอียดอยู่ในรายงานมวลชนสัมพันธ์พร้อมภาพประกอบ
ส่วนประเด็นเรื่องปลาขนาดใหญ่ เนื่องจากมีการออกแบบโรงไฟฟ้าเพื่อป้องกันและลดผลกระทบในการที่จะให้ความเร็วของน้ำที่ไหลเข้า 0.3 เมตรต่อวินาที ซึ่งเป็นความเร็วที่ค่อนข้างต่ำมาก เพราะฉะนั้นปลาใหญ่หรือปลาขนาดย่อมๆ จะไม่สามารถหลุดเข้าไปได้ นอกจากนี้มีตะแกรง 2 ชั้น ตะแกรงขนาดหยาบซึ่งป้องกันปลาขนาดใหญ่ตั้งแต่ก่อนเข้าไปในโรงไฟฟ้า คือจะกันปลาใหญ่ก่อน หลังจากนั้นจะมีตะแกรงละเอียดสำหรับป้องกันปลาตัวเล็ก แต่อย่างไรก็ตามแพลงตอนมีขนาดเล็กมากจนไม่สามารถป้องกันได้ บริเวณที่สูบน้ำเข้าเป็นบริเวณท่าเรือ ซึ่งด้านกฎของความปลอดภัยไม่ควรจะมีเรือหาปลาเข้าไปในบริเวณนั้น

Coal will be heavily compacted to ensure that no oxygen will cause unnecessary combustion.
Additionally, water spraying will be carried out corresponding to the speed 
     and direction of the prevailing wind. Finally, the long-term stockpile will be 
     covered to protect the stockpile from the elements.

จะมีระบบสเปรย์น้ำและปูด้วยวัสดุกันซึมรองใต้ลานกองถ่านหินเพื่อไม่ให้น้ำซึมลงดิน โครงการได้ทำระบบระบายน้ำเพื่อนำน้ำไปตกตะกอนที่บ่อพักน้ำจะถูกจะถูกบำบัด และนำกลับมาใช้ไม่มีการปล่อยลงสู่ทะเล ลานกองถ่านหินมีทั้งสิ้นจำนวน 3 กอง มีตัวสเปรย์น้ำ 17 ตัว ทำงานอัตโนมัติตามแรงลมที่วัดได้ กองถ่านสำรองจะบดอัดเป็นรูปทรงปิระมิดหัวตัดและสเปรย์สารประเภทโพลิเมอร์ลักษณะคล้ายกากน้ำตาล เพื่อยึดเกาะไม่ให้ฟุ้งกระจายในกรณีที่เกิดพายุรุนแรง

Air Quality Impact Monitoring Measures

Water used in the power plant is divided into 2 types:
Fresh Water is water used by the power plant in the production process, port, coal yard, and within office buildings. Wastewater management is as follows: * A Waste Water Treatment Plant is provided. * Rainwater from the port and coal yard is treated and recycled.
Sea Water is pumped in for cooling and for use in the sulfur dioxide gas treatment system. Two layers of screens (Traveling Screen and Bar Screen) are installed to prevent marine life from entering the cooling system. The speed of the seawater pumped in for cooling is also controlled. These screens help any marine life that might enter to easily escape the cooling water intake channel. Furthermore, an aeration pond has been installed at the cooling water discharge point to adjust the water's temperature and pH value before it is discharged into the sea. The system is also inspected, and an annual equipment maintenance plan is prepared. Continuous and regular monitoring of seawater quality around the BLCP Power Station is also conducted.

FuelThe quality of imported coal will be inspected for every shipment to ensure it meets specified standards from a reliable central agency.
AirParticulate matter will be monitored at 3 locations: the north and south sides of the coal yard, and in Takuan community.
Continuous Emission Monitoring (CEMs) equipment is installed in the middle of the stack, and air quality discharged from the stack is measured by environmental consultants every 6 months.
Four Air Quality Monitoring Stations (AQMS) are installed around the BLCP Power Station, and air quality at the AQMS stations is measured by environmental consultants every 6 months.

The quality of treated water is monitored by environmental consultants every 6 months.
Automatic monitoring instruments for temperature, pH, residual chlorine, and COD are installed at the water discharge point into the sea.
Changes in seawater temperature in Map Ta Phut Bay are monitored at 13 points around the discharge point by environmental consultants every 3 months.

AirA sulfur oxide gas treatment system is installed. For nitrogen oxides, the Company designed the furnace to reduce the amount of such gases produced.
WaterNo wastewater is discharged from the power plant. Only seawater, pumped in for cooling and sulfur oxide gas removal, is adjusted for temperature and pH before being discharged into the sea, ensuring its temperature is close to when it was drawn in.
Coal AshIt is sold to the cement manufacturing industry. Additionally, it can be used in concrete block production, or for landfill and ground improvement.

The Company prioritizes environmental matters, from selecting clean coal technology to implementing measures to mitigate environmental impacts.

This is achieved by selecting bituminous coal as fuel, which is high-quality coal with low sulfur content, with a maximum of 0.70% and an annual average of no more than 0.45% (compared to lignite coal at Mae Moh with approximately 3-5% sulfur). Modern machinery with efficient environmental control equipment is used for electricity generation, including the installation of sulfur oxide gas removal systems. Furnaces are chosen to control the generation of nitrogen oxides to low levels. Electrostatic precipitators are installed. Treated air is discharged through a 200-meter-high stack to reduce air pollution. Additionally, there is a wastewater treatment plant and a pond to adjust the temperature and pH of cooling water before discharge into the sea to mitigate water pollution. Environmental conditions, both water and air, are regularly monitored using automatic instruments and re-checked by independent agencies, in cooperation with environmental authorities for inspections.

It is BLCP's core policy not only to control environmental impacts according to government-mandated standards, which will not affect public health, but also to strive to exceed these government standards. If the Company fails to comply with these regulations, regulatory agencies can immediately take legal action against the Company.

Seawater is used to convert sulfur oxides into sulfate radicals, which are naturally present in seawater. Therefore, no heavy metal contamination in seawater results from this process.

According to the EPC Turnkey contract, the wastewater treatment pond will be designed to match and suit the size and operational requirements after the power plant construction commences.

The land reclamation is an operation by the Industrial Estate Authority. BLCP is merely a land lessee.

This is because a deep-sea port is required for coal transshipment by vessel. Currently, the area is only 12 meters deep, but BLCP requires a port approximately 17 meters deep, necessitating sand dredging. The dredged sand will be used to prepare the site for power plant construction.

During handling, cranes will transfer coal from vessels into a semi-enclosed conveyor system. Water will be continuously sprayed at the chute before it enters the conveyor system to prevent coal dust dispersion. Afterward, it will be transported into a fully enclosed conveyor system.

Before vessels depart from ports in Australia and Indonesia, coal quality is inspected by agencies recognized by the power plant and coal suppliers before shipment to Thailand. Another inspection is conducted at the Company's port in Map Ta Phut Industrial Estate.

Cooling water uses seawater pumped into the system to carry away heat from machinery, causing the water temperature to rise. It is treated by discharging into a holding pond and pumping air into it to increase the surface area for heat dissipation. Afterward, it is discharged through a 500-600 m long drainage pipe to adjust the temperature. The discharge point for cooling water is monitored by instruments, with the Department of Industrial Works stipulating that the maximum discharge temperature must not exceed 40°C. The temperature around the discharge point within a 500 m radius must not differ from the seawater temperature by more than 3°C. Temperature measurements are taken at approximately 13 points around the project throughout its 25-year lifespan.

The Company has hired a specialized dredging company from Belgium, with dredging of the navigation channel expected to commence around early 2546. The dredging will utilize a Cutter Suction Dredger with a tungsten carbide cutter head to excavate sand sediment while simultaneously pumping it back up. This method is highly efficient, capable of pumping up to 90% of sand sediment, which is then transported through pipes and discharged into the leased area requiring additional landfill. Furthermore, there is a committee overseeing the action plan for preventing, mitigating, and monitoring environmental impacts of the coal handling port project, established according to the conditions specified in the EIA.

Approximately 5.38 million cubic meters of seawater are used per day. Biologists have identified the types of plankton drawn in, and it has also been proven that this portion of plankton can regenerate daily. However, this does not mean the Company has the right to destroy plankton. Although the Company cannot prevent their intake, it can facilitate their regeneration. The Company has consulted with communities, especially fishing communities. One method the Company employs is to create new marine life, such as releasing crabs in cages to re-establish the initial marine food chain. Details are available in the public relations report with illustrations.
Regarding large fish, the power plant is designed to prevent and mitigate impacts by ensuring an intake water velocity of 0.3 meters per second, which is very low. Therefore, large or medium-sized fish cannot enter. Additionally, there are two layers of screens: a coarse screen that prevents large fish from entering the power plant initially, followed by a fine screen for smaller fish. However, plankton are too small to be screened out. The water intake area is within the port, where, for safety reasons, fishing boats should not enter.

Coal piles are compacted to prevent oxygen ingress, which could lead to spontaneous combustion.
Additionally, water is sprayed with adjustable intensity according to wind speed.

There will be a water spray system and an impermeable liner beneath the coal yard to prevent water seepage into the ground. The project has implemented a drainage system to direct water to a sedimentation pond, where it will be treated and recycled, with no discharge into the sea. There are a total of 3 coal piles, equipped with 17 automatic water sprayers that operate according to measured wind speed. Reserve coal piles are compacted into a truncated pyramid shape and sprayed with a polymer substance, similar to molasses, to bind the coal and prevent dispersion in the event of severe storms.